News Releases

  • Missouri River upper basin runoff continues below average forecast

    The updated 2025 calendar year runoff forecast for the Missouri River Basin above Sioux City, Iowa, continues to be below average. March runoff in the Missouri River Basin above Sioux City was 2.3 million acre-feet, 76% of average.
  • Agencies push Columbia River environmental review

    The U.S. Army Corps of Engineers (USACE) and Bureau of Reclamation (Reclamation), or co-lead agencies, are pushing back virtual public scoping meetings they previously scheduled for the week of April 7, 2025. The co-lead agencies will also extend the scoping period for a Supplemental Environmental Impact Statement (SEIS) for the Columbia River System Operations.
  • Virtual Missouri River water management public meetings set for April

    Two meetings to hear from the public about planned operation of the Missouri River Mainstem System will be held the first week in April.
  • Spring Missouri River public meetings to be virtual

    Virtual meetings on Missouri River Mainstem Reservoir system operations are in the process of being scheduled. Meeting dates and times will be announced as the details are finalized. In-person public meetings on Missouri River Mainstem Reservoir system operations, which were scheduled for March 19, 31 and April 2 have been canceled.
  • Gavins Point releases increasing for navigation flow support; Upper basin runoff stays below average

    The updated 2025 calendar year runoff forecast for the Missouri River Basin above Sioux City, Iowa, continues to be below average. February runoff in the Missouri River Basin above Sioux City was 1.0 million acre-feet, 91% of average. “Runoff into the reservoir system was slightly below average for the month of February and conditions across most of the basin remain dry,” said John Remus, chief of the U.S. Army Corps of Engineers’ Missouri River Basin Water Management Division.
  • Agencies extend Columbia River environmental review, delay public meetings

    Two federal agencies are extending the public scoping period for the Columbia River System Operations Supplemental Environmental Impact Statement (SEIS.) The U.S. Army Corps of Engineers (USACE) and the Bureau of Reclamation (Reclamation), or co-lead agencies, are also adjusting the timing of the public meetings to the week of April 7, 2025.