  • Reservoir release changes at Fort Randall and Gavins Point dams

    Excessive rainfall in eastern South Dakota, northeastern Nebraska, and northwestern Iowa, has led to increased runoff downstream of Gavins Point Dam. The lower releases will begin today, and will continue through June 23. Because of the lower releases, the pool elevation at Gavins Point Dam will increase about 2 feet. The elevation as of midnight, June 21, was 1207.1 feet.
  • Second peak of Fort Peck flow test resuming

    Releases from Fort Peck will begin stepping up as part of the second peak of the Fort Peck flow test starting today. Releases from Fort Peck will be gradually increased, starting today, June 17, to reach a peak flow of 20,000 cubic feet per second on Sunday, June 23.
  • Next phase of Fort Peck flow test delayed

    The second peak from Fort Peck Dam was initially scheduled to begin tomorrow, June 13 but will be delayed until at least June 17.
  • May runoff slightly above average; Fort Peck flow test continues

    Active rainfall patterns across the Midwest provided much needed moisture to several portions of the Missouri River Basin. Large areas of Montana, North Dakota, Wyoming, eastern South Dakota, and eastern Nebraska received more than 200% of normal precipitation for the month of May. However, central South Dakota, western Nebraska, and eastern Colorado received as little as 25% of normal precipitation.
  • Missouri River Basin runoff forecast improves but remains below average; Fort Peck Flow Test underway

    As warmer weather moves into the Missouri River Basin, spring precipitation brought some much-needed moisture throughout the basin. For the month of April, runoff was 2.1 million acre-feet, 71% of average, for the basin above Sioux City, Iowa. The annual runoff forecast for the upper Missouri River Basin above Sioux City is 19.2 MAF, 75% of average, and 1.7 MAF higher than last month’s forecast.
  • Weekly calls designed to keep public updated on status of Fort Peck test flows

    Beginning Weds., April 24, the Missouri River Water Management Division will host weekly virtual meetings to provide updates on the status of test flows from Fort Peck Dam in Montana. Test flows to comply with the 2018 Biological Opinion will begin Fri., April 26. Calls will be held each Wednesday, at 1 p.m. Central Time, (12 p.m. Mountain Time) Information on accessing the public meetings can be found at https://www.nwd.usace.army.mil/MRWM/Public-Meetings/Meetings.