Turbine and Generator |
Location |
Description |
Date |
Fort Worth: |
Sam Rayburn – Turbine Rehab 2 Propeller Runner Repl, 180” D, 41,300 HP, 70’ Head, 85.7 RPM |
FY28 or later |
Fort Worth: |
Sam Rayburn – Generator Rehab 2 Rewinds, 31.5MVA |
FY26 or later |
Kansas City: |
HS Truman – Generator Rehab 6 Rewinds, 28.4 MVA |
FY26 or later |
Little Rock: |
Bull Shoals – Turbine and Generator Rehab |
FY26 or later |
|
4 Francis Runner Repl, 152.5” D, 52,000 HP, 190’ Head, 128.6 RPM, Potential Uprate |
|
|
4 Francis Runner Repl, 152.5” D, 62,000 HP, 190’ Head, 128.6 RPM |
|
|
4 Rewinds, 54 MVA, Coils |
|
|
4 Rewinds, 54.5 MVA, Coils |
|
Little Rock: |
Dardanelle – Cavitation Repairs |
FY28 |
Little Rock: |
Greers Ferry – Generator Rewind 2 Rewinds, 58,105 kVA, multi-turn coils |
FY25 |
Mobile: |
Allatoona – Turbine Rehab 2 Francis Runner Repl, 165” D, 50,000 HP, 135’ Head, 112.5 RPM, Potential Uprate |
FY32 |
Mobile: |
West Point – Turbine Rehab 2 Fixed Blade Propeller Repl, 230” D, 51,500 HP, 58’ Head, 100 RPM, Potential Uprate |
FY30 |
Mobile: |
West Point – U1 Generator Rewind 1 Rewind, Francis, 3.75 MVA, Coil |
FY28 |
Nashville: |
Wolf Creek – Turbine and Generator Rehab |
FY27 |
|
6 Francis Runner Repl w/ DO, 175” D, 62,500 HP, 160 Head, 105.9 RPM, Potential Uprate |
|
|
4 Rewinds, 50 MVA, Coils |
|
Nashville: |
Cordell Hull – Turbine and Generator Rehab 3 Kaplan Runner Repl, 290” D, 58,200 HP, 44’ Head, 65.5 RPM 3 Rewinds, 37MVA |
FY29 |
Portland: |
Bonneville – Powerhouse 2 Generator Rehab: Main & Fish 8 Main Unit Rewinds, 70 MVA, 2 Fish Unit Rewinds 13.8 MVA |
FY29 |
Portland: |
John Day – Fish Turbine Pump Units 2 Francis Runner Repl, ~34” D, 1,050 HP, 83.5’ Head, 525 RPM |
FY27 |
Portland: |
John Day – Turbine Replacement and Generator Rewind Up to 16 Kaplan Runner Repl, 312” D, 212,400 HP, 103’ Head, 90 RPM, Fixed and adjustable blade turbine runners, Improved fish passage turbine design 16 Rewinds, 163 MVA, Bars, Potential Uprate |
FY25 |
Portland: |
Foster – Turbine Refurbishment 2 Kaplan refurb, 95” D, Refurbish blade operating mechanisms, Generator Slip Ring Repair |
FY26 or later |
Portland: |
Lost Creek – Generator Windings 2 Units, 25.8MVA |
FY29 |
Seattle: |
Albeni Falls – Generator Rewind and Bearing Rehabilitation 3 Units, ~20MVA, Coil |
FY30 |
Seattle: |
Libby – Turbine Runner Replacement and Generator Rewind |
FY27 |
|
4 Francis Runners, 179” D, 165,000 HP, 300’ Head, 128.6 RPM |
|
|
5 Generator Rewinds, 121 MVA, Coil |
|
Seattle: |
Chief Joseph – Generator Rewind Units 17-27 11 Rewinds, Francis, 115 MVA, Bar |
FY30 |
Tulsa: |
Denison – Station Service Units Rehab or Replace 2 600 kW turbines, 480V generators |
FY26 or later |
Tulsa: |
Keystone – Turbine Rehab 2 Fixed Blade,195.375” D, 49,000 HP, 74’ Head, 120 RPM, Potential Uprate |
FY26 or later |
Tulsa: |
Eufaula – Generator Rewind 3 Francis, 31,579 kVA, multi-turn coils,182” D, 41,500 HP, 96’ Head, 100 RPM |
FY25 |
Walla Walla: |
Little Goose – Discharge Ring Upgrade and Turbine Blade Cavitation 6 Kaplan, 312” D, 212,400 HP, 90 RPM |
FY25 |
Walla Walla: |
Lower Granite – Blade Sleeve Upgrade 6 Kaplan, 312” D, 212,400 HP, 90 RPM |
FY25 |
Excitation System |
Location |
Description |
Date |
Charleston: |
St. Stephen – Digital Static Excitation System Retrofit 3 Units |
FY26 |
Fort Worth: |
Sam Rayburn – Digital Static Excitation System Replacement |
FY25 or later |
Little Rock: |
Beaver – Analog to Digital Static Excitation System Replacement |
FY25 |
Little Rock: |
Greers Ferry – Analog to Digital Static Excitation System Replacement |
FY25 |
Little Rock: |
Table Rock – Analog to Digital Static Excitation System Replacement |
FY25 |
Mobile: |
West Point – U1 Rotating to Digital Static Excitation System Replacement 1 Unit, under investigation |
FY28 |
Mobile: |
Walter F. George – Digital Static Excitation System Retrofit 4 Units |
FY26 |
Portland: |
John Day – Digital Static Excitation System Controls Replacement 16 Units, under investigation |
FY26 or later |
Portland: |
The Dalles – Digital Static Excitation System Replacement 21 Main Units and 2 Fish Units, under investigation |
FY28 |
Portland: |
Willamette Valley (under investigation): |
|
|
Big Cliff – Digital Static Excitation System Controls Replacement 1 Unit |
FY32 |
|
Cougar – Digital Static Excitation System Replacement 2 Units |
FY30 |
|
Dexter – Digital Static Excitation System Replacement 1 Unit |
FY30 |
|
Detroit – Digital Static Excitation System Controls Replacement 2 Units |
FY28 |
|
Foster – Digital Static Excitation System Controls Replacement 2 Units |
FY33 |
|
Green Peter – Digital Static Excitation System Controls Replacement, 2 Units and 1 Fish Unit |
FY29 |
|
Hills Creek – Digital Static Excitation System Replacement, 2 Units |
FY28 |
|
Lookout Point – Digital Static Excitation System Replacement, 3 Units |
FY30 |
Portland: |
Lost Creek – Digital Static Excitation System Replacement 2 Units, under investigation |
FY30 |
Savannah: |
J Strom Thurmond – Digital Static Excitation System Replacement, 7 units |
FY26 |
Savannah: |
Hartwell – Digital Static Excitation System Retrofit, 5 Units |
FY26 |
Savannah: |
Richard B. Russel – Digital Static Excitation System Retrofit, 8 Units |
FY26 |
Seattle: |
Albeni Falls – Digital Static Excitation System Controls Replacement 3 Units, under investigation |
FY30 |
Seattle: |
Chief Joseph – Station Service Digital Static Excitation System Replacement 2 Units |
FY25 |
Seattle: |
Chief Joseph – Units 1-16 Digital Static Excitation System Controls Replacement 16 Units |
FY24 |
Tulsa: |
Denison –Digital Static Excitation System Controls Replacement 2 Units, under investigation |
FY26 |
Tulsa: |
Keystone – Excitation System Replacement |
FY27 |
Tulsa: |
Tenkiller Ferry – Digital Static Excitation System Controls Replacement 2 Units, under investigation |
FY26 |
Tulsa: |
Webbers Falls – Digital Static Excitation System Controls Replacement 2 Units, under investigation |
FY26 |
Wilmington: |
John H. Kerr – Digital Static Excitation System Retrofit, 2 Station Service Units |
FY26 |
Wilmington: |
Philpott – Digital Static Excitation System Retrofit, 1 Station Service Unit |
FY26 |
Governor |
Location |
Description |
Date |
Little Rock: |
Greers Ferry – Governor Rehab |
FY27 |
Mobile: |
Buford – Governor Upgrades |
FY26 |
Mobile: |
Walter F. George – Governor Upgrades |
FY27 |
St. Louis: |
Clarence Cannon – Governor Upgrades |
FY24 or later |
Wilmington: |
John H. Kerr – Digital Governor Supply Upgrades |
FY25 |
Crane and Hoist |
Ft. Worth: |
Sam Rayburn – Draft Tube Crane Replacement |
FY26 or later |
Kansas City: |
H.S. Truman – Draft Tube Crane Replacement |
FY25 or later |
Little Rock: |
Beaver – Bridge Crane Rehab |
FY25 |
Little Rock: |
Bull Shoals – Draft Tube Crane Rehab |
FY26 |
Little Rock: |
Dardanelle – Bridge Crane Replacement |
FY25 |
Little Rock: |
Greers Ferry – Bridge Crane Rehab |
FY25 |
Little Rock: |
Greers Ferry – Draft Tube Crane Rail, Cable, and Trolley Rehab |
FY26 |
Little Rock: |
Table Rock – Bridge Crane Rehab |
FY26 |
Mobile: |
Allatoona – Headgates Machinery and Controls Rehab |
FY26 |
Mobile: |
Buford – Headgates Machinery and Controls Rehab |
FY26 |
Mobile: |
Walter F George – Headgates Machinery and Controls Rehab |
FY27 |
Mobile: |
West Point – Headgates Machinery and Controls Rehab |
FY27 |
Nashville: |
Wolf Creek – Bridge Crane Rehab (MATOC) |
FY25 |
Nashville: |
Cheatham – Intake Crane Replacement (MATOC) |
FY25 |
Nashville: |
Cordell Hull – Intake Crane Replacement (MATOC) |
FY26 |
Nashville: |
Cordell Hull – Bridge Crane Rehab (MATOC) |
FY27 |
Nashville: |
Cheatham – Bridge Crane Rehab (MATOC) |
FY29 |
Omaha: |
Gavins Point – Intake Crane and Rail Replacement |
FY25 |
Portland: |
John Day – Bridge Crane Rails |
FY26 |
Portland: |
John Day – Tailrace Crane |
FY28 |
Portland: |
The Dalles – Spillway Crane |
FY28 |
Portland: |
Green Peter Bridge Crane |
FY25 |
Portland: |
Lost Creek Bridge Crane |
FY28 |
Savannah: |
RB Russell – Bridge Crane Rehab |
FY29 |
Savannah: |
RB Russell – Draft Tube Crane Replacement |
FY27 |
Seattle: |
Albeni Falls – 250-Ton Powerhouse Bridge Crane Rehabilitation |
FY24 |
Seattle: |
Libby – 20-Ton Selective Withdraw Gantry Crane Rehabilitation |
FY27 |
Tulsa: |
Eufaula – Bridge Crane Rehab |
FY27 |
Tulsa: |
Fort Gibson – Draft Tube Crane Rehab |
FY26 |
Tulsa: |
Fort Gibson – Bridge Crane Rehab |
FY26 |
Tulsa: |
Keystone – Draft Tube Crane Rehab |
FY26 |
Walla Walla: |
Lower Monumental – Bridge Crane Wheel and Drive System Upgrade |
FY24 |
Walla Walla: |
Ice Harbor – Intake Gate Hydraulic System Upgrades |
FY25 |
Walla Walla: |
Lower Granite – Intake Gate Hydraulic System |
FY25 |
Walla Walla: |
Little Goose – Intake Gate Hydraulic System |
FY26 |
Walla Walla: |
Lower Monumental – Intake Gate Hydraulic System |
FY26 |
Walla Walla: |
Little Goose – Tailrace Crane Replacement |
FY29 |
Walla Walla: |
Lower Granite – Tailrace Crane Replacement |
FY28 |
Walla Walla: |
McNary – Second Bridge Crane PLC |
FY24 |
Metal Fabrication (Bulkhead, Gate, Platform) |
Location |
Description |
Date |
Fort Worth: |
HSS Gates and Bulkheads |
FY25 |
Mobile: |
Allatoona – Headgate and Machinery Rehab |
FY26 |
Mobile: |
Buford – Headgate and Machinery Rehab |
FY26 |
Mobile: |
Walter F. George – Headgate and Machinery Rehab |
FY27 |
Mobile: |
West Point – Headgate and Machinery Rehab |
FY27 |
Portland: |
Bonneville – Headgate Repair Pit Rehab |
FY25 |
Portland: |
Bonneville – Spillway Gate Repair & Storage Pit |
FY24 |
Portland: |
Bonneville – B2 Submerged Traveling Screen Rehab |
FY26 |
Portland: |
Bonneville – Spillway Gates |
FY34 |
Portland: |
John Day – Spillway Gate Brakes and Gearboxes |
FY28 |
Portland: |
Big Cliff – Intake Gates and Trash Racks Replacement |
FY26 |
Portland: |
Detroit – Intake Gates Replacement & Trash Racks Rehab. |
FY27 |
Portland: |
Green Peter – Trashracks and Intake Gates |
FY26 |
Portland: |
Dexter - Trashracks and Intake Gates |
FY26 |
Portland: |
Foster - Trashracks and Intake Gates |
FY29 |
Seattle: |
Albeni Falls – Intake Gate Replacement |
FY26 |
Seattle: |
Albeni Falls – Intake Gate Rehab |
FY27 |
Seattle: |
Albeni Falls – Trashracks Rehab |
FY28 |
Seattle: |
Albeni Falls – Turbine Maintenance Platform |
FY24 |
Seattle: |
Albeni Falls – Turbine Maintenance Platform |
FY24 |
Seattle: |
Chief Joseph – Intake Gates and Cylinder Rehab or Replacement |
FY27 |
Seattle: |
Chief Joseph – Turbine Maintenance Platform |
FY25 |
Seattle: |
Libby – Selective Withdrawal Pressure Relief Bulkhead |
FY28 |
Tulsa: |
Broken Bow – Rehab Intake Gates and Controls |
FY27 |
Tulsa: |
Denison – Intake Gates and Hoists Replacement |
FY26 |
Tulsa: |
Fort Gibson – Intake Gates and Hoists |
FY27 |
Tulsa: |
Tenkiller – Draft Tube Gate Bulkhead & Lifting Beam |
FY24 |
Walla Walla: |
McNary – Turbine Maintenance Platform |
FY25 |
Walla Walla: |
Ice Harbor – Turbine Maintenance Platform |
FY25 |
Walla Walla: |
Lower Monumental – Draft Tube Bulkhead Replacement |
FY27 |
Balance of Plant |
Little Rock: |
Bull Shoals – HVAC System Replacement |
FY29 |
Portland: |
Bonneville – Powerhouse 1 HVAC |
FY27 |
Portland: |
John Day – Powerhouse Floor Drainage Improvements |
FY24 |
Portland: |
John Day – Powerhouse Security System Upgrades |
FY25 |
Portland: |
John Day – Powerhouse Emergency Notification System |
FY26 |
Portland: |
John Day – Vibration and Air Gap Monitoring |
FY26 |
Portland: |
John Day – Synchronous Condensing Reconfiguration |
FY29 |
Portland: |
The Dalles – Station Air System |
FY25 |
Seattle: |
Chief Joseph – HVAC and Controls Upgrades |
FY30 |
Seattle: |
Chief Joseph – Powerhouse Sump Pump and Controls |
FY24 |
Walla Walla: |
Ice Harbor – Powerhouse HVAC System Upgrade |
FY26 |
Walla Walla: |
Little Goose – Powerhouse HVAC System Upgrade |
FY28 |
Walla Walla: |
Lower Monumental – Powerhouse HVAC System Upgrade |
FY26 |
Walla Walla: |
Lower Granite – Heat Pumps / HVAC Upgrade |
FY28 |
Fire Suppression & Fire Protection/Detection |
Location |
Description |
Date |
Ft. Worth: |
Sam Rayburn – Fire Detection System |
FY26 or later |
Kansas City: |
Stockton – Fire Protection System Replacement |
FY26 or later |
Kansas City: |
HS Truman – Fire Protection System Replacement |
FY26 or later |
Little Rock |
Beaver – CO2 System Replacement |
FY26 |
Little Rock: |
Dardanelle – CO2 System Replacement |
FY26 |
Little Rock: |
Greers Ferry – Fire Suppression (clean agent) and Detection |
FY25 |
Little Rock: |
Norfork – Fire Suppression (clean agent) and Detection System Replacement |
FY25 |
Little Rock: |
Ozark – Fire Detection |
FY26 |
Little Rock: |
Table Rock – Fire Detection |
FY26 |
Mobile: |
Buford – Generator Fire Suppression System Replacement |
FY29 |
Mobile: |
Carters – Generator Fire Suppression System Replacement |
FY30 |
Mobile: |
Jones Bluff (RF Henry) – Generator Fire Suppression System |
FY31 |
Portland: |
Bonneville – Transformer Fire Protection |
FY30 |
Portland: |
Bonneville – Generator Fire Protection |
FY27 |
Portland: |
John Day – Transformer Fire Protection |
FY26 |
Portland: |
The Dalles – Generator Fire Protection |
FY26 |
Portland: |
The Dalles – Transformer Fire Protection |
FY29 |
Portland: |
Dexter – Fire Detection/HVAC/Life Safety |
FY28 |
Portland: |
Foster – Fire Detection, HVAC, & Life Safety |
FY27 |
Portland: |
Lost Creek – Fire Detection & Fire Protection |
FY28 |
Savannah: |
Hartwell – Transformer Fire Suppression System |
FY32 |
Seattle: |
Albeni Falls – CO2 Fire Suppression System |
FY29 |
Seattle: |
Chief Joseph – Facility Plant Fire Detection and Protection |
FY27 |
Seattle: |
Libby – CO2 Fire Suppression System |
FY30 |
Walla Walla: |
Dworshak – Transformer Deluge System Modifications |
FY27 |
Walla Walla: |
Ice Harbor – Control Room Life Safety/Fire Alarm System Upgrades |
FY25 |
Walla Walla: |
Ice Harbor – Transformer Deluge Fire Protection System Upgrades |
FY28 |
Walla Walla: |
Little Goose – Control Room Life Safety/Fire Alarm System Upgrades |
FY26 |
Walla Walla: |
Lower Monumental – Control Room Life Safety/Fire Alarm System Upgrades |
FY27 |
Walla Walla: |
Lower Granite – Control Room Life Safety/Fire Alarm System Upgrades |
FY26 |
Walla Walla: |
McNary – Control Room Life Safety/Fire Alarm System Upgrades |
FY25 |
Controls |
Portland: |
John Day – Control System Upgrade |
FY27 |
Portland: |
The Dalles – Control Room Modernization |
FY26 |
Seattle: |
Chief Joseph – Annunciation Upgrade |
FY27 |
Seattle: |
Chief Joseph – Powerhouse Control Room Reliability Upgrades |
FY27 |
Seattle: |
Chief Joseph – Protective Relays |
FY28 |
Kansas City: |
Harry S Truman – Intake Gate Controls |
FY25 |
Walla Walla: |
Little Goose – Powerhouse Controls/Annunciation |
FY25 |
Walla Walla: |
Lower Monumental – Powerhouse Controls/Annunciation |
FY26 |
Walla Walla: |
Ice Harbor – Powerhouse Controls/Annunciation |
FY28 |
DC/Preferred AC Systems |
Nashville: |
Wolf Creek – DC/Preferred AC Systems Install |
FY24 |
Nashville: |
J Percy Priest – DC/Preferred AC Systems Install |
FY26 |
Portland: |
Bonneville – Powerhouse 1 Preferred AC/DC Improvements |
FY26 |
Electrical Low Voltage (Less than 1,000V) |
Location |
Description |
Date |
Kansas City: |
Stockton – 480V Switchgear Replacement |
FY26 |
Little Rock: |
Bull Shoals – 480V Switchgear and MCC |
FY25 |
Little Rock: |
Beaver – 480V Switchgear and MCC |
FY24 |
Little Rock: |
Table Rock – 480V Switchgear and MCC |
FY24 |
Little Rock: |
Ozark – 480V Switchgear and MCC |
FY25 |
Little Rock: |
Dardanelle – 480V Switchgear and MCC |
FY25 |
Omaha: |
Fort Peck – PH1 Cubicle Room Switchgear Upgrade |
FY24 or FY25 |
Portland: |
Lost Creek – Motor Control Centers and Cabling |
FY29 |
Seattle: |
Chief Joseph – 480V Station Power SQ 4&5, SU17-27 Replacement |
FY29 |
Seattle: |
Chief Joseph – 480V Station Power DSQ 1&2, SQ1&3 Replacement |
FY26 |
Tulsa: |
Broken Bow – 480V Switchgear and MCC |
FY27 |
Tulsa: |
Eufaula – Motor Control Centers Replacement |
FY26 |
Tulsa: |
Fort Gibson – 480V Switchgear and Transformers |
FY24 |
Vicksburg: |
Narrows – 480V Switchgear and MCC Replacement |
FY27 |
Vicksburg: |
DeGray – 480V Switchgear and MCC |
FY26 |
Vicksburg: |
Blakely Mountain – 480V Switchgear and MCC |
FY25 |
Electrical Medium Voltage (More than 1,000V) |
Location |
Description |
Date |
Ft. Worth: |
Sam Rayburn – 15kV Switchgear Replacement |
FY26 |
Little Rock: |
Bull Shoals – Modernization Electrical Install |
FY27 |
Little Rock: |
Ozark – Replace 161-kV Switches |
FY25 |
Little Rock: |
Ozark – Replace 15kV Generator Cables |
FY25 |
Little Rock: |
Greers Ferry – 15kV Breakers/Switchgear and Station Service Transformer Replacement |
FY26 |
Nashville: |
Center Hill – Station Service |
FY27 |
Nashville: |
Old Hickory – Station Service |
FY28 |
Portland: |
Bonneville – Powerhouse 1 Main Unit Breaker Replacement Upgrades |
FY25 |
Portland: |
Bonneville – Powerhouse 1 Isophase Bus/Duct |
FY30 |
Portland: |
Bonneville – Powerhouse 2 Isophase Bus/Duct |
FY29 |
Portland: |
John Day – Isophase Bus & Duct |
FY27 |
Portland: |
The Dalles – Isophase Bus & Duct |
FY28 |
Portland: |
John Day – XJ Disconnect Switches |
FY32 |
Portland: |
Green Peter Main Unit Breakers and Electrical Reliability Upgrades |
FY26 |
Portland: |
Cougar Electrical Reliability (Station Service) Upgrades |
FY29 |
Portland: |
Hills Creek – Main Unit Breakers and Electrical Reliability Upgrades |
FY25 |
Seattle: |
Albeni Falls – Emergency Diesel Generator |
FY28 |
Seattle: |
Chief Joseph – Isophase Bus Rehab Unit 1-16 |
FY24 or FY25 |
Seattle: |
Chief Joseph – SF6 Breaker Refurbishment |
FY27 |
Seattle: |
Chief Joseph – XJ Breaker Disconnect |
FY26 |
Seattle: |
Chief Joseph – Isophase Bus Rehab Unit 17-27 |
FY30 |
Seattle: |
Libby – SF6 Breaker Refurbishment |
FY27 |
Tulsa: |
Denison – Switchyard Power Circuit Breaker Replacement |
FY24 |
Tulsa: |
Tenkiller Ferry – Station Service System and Transformer Feeders Replacement |
FY24 |
Vicksburg: |
Blakely Mountain – Oil Circuit Breaker Replacement Supply |
FY25 or later |
Vicksburg: |
DeGray – Oil Circuit Breaker Replacement Supply |
FY25 or later |
Vicksburg: |
Narrows – Oil Circuit Breaker Replacement Supply |
FY25 or later |
Walla Walla: |
Little Goose – 500kV Transmission Line Configuration Upgrade |
FY27 |
Walla Walla: |
Little Goose – Isophase Bus Reconfiguration |
FY28 |
Walla Walla: |
Lower Monumental – 500kV Transmission Line Configuration Upgrade |
FY27 |
Walla Walla: |
Lower Monumental – Isophase Bus Reconfiguration |
FY28 |
Walla Walla: |
Lower Granite – 500kV Transmission Line Configuration Upgrade |
FY26 |
Walla Walla: |
Lower Granite– Isophase Bus Reconfiguration |
FY28 |
Large Power Transformer |
Location |
Description |
Date |
Little Rock: |
Bull Shoals – Main Unit 3 Transformer Supply and Install (SF6) |
FY24 |
Little Rock: |
Bull Shoals – Transformer Supply and Install (SF6) |
FY27 |
Little Rock: |
Beaver – Transformer Supply and Install |
FY27 |
Little Rock: |
Ozark – GSU Transformer Repairs |
FY26 |
Mobile: |
West Point – U1 Transformer Replacement |
FY28 |
Nashville: |
Cheatham – Transformer Supply and Install |
FY29 |
Omaha: |
Fort Peck – T4 / T5 Transformer Replacement – Supply |
FY25 |
Omaha: |
Fort Peck – T4 / T5 Transformer Replacement – Install |
FY27 |
Omaha: |
Oahe – GSU Transformer Replacement – Supply |
FY25 |
Omaha: |
Oahe – GSU Transformer Replacement – Install |
FY27 |
Portland: |
John Day – GSU Transformer Replacement – Supply |
FY27 |
Portland: |
The Dalles – Main Unit Transformers 9-11 Repair |
FY25 |
Portland: |
The Dalles – Main Unit Transformers 9-11 Replacement Supply |
FY28 |
Portland: |
Detroit – Main Unit Transformer Replacement Supply |
FY25 |
Portland: |
Detroit – Main Unit Transformer Replacement Install |
FY26 |
Portland: |
Dexter – GSU Transformer |
FY27 |
Portland: |
Foster – GSU Transformer |
FY28 |
Portland: |
Lookout Point – GSU Transformers |
FY27 |
Seattle: |
Chief Joseph – Transformer Replacement (T1-4) |
FY30 |
Seattle: |
Libby – Transformer Refurbishment (T2) |
FY28 |
Tulsa: |
Keystone – GSU Rehab/Replacement |
FY28 |
Walla Walla: |
Little Goose – GSU T2 spare supply |
FY24 |
Walla Walla: |
Lower Snake River – GSU T1 spare supply |
FY24 |
Walla Walla: |
Ice Harbor – Transformer 1-5 Replacement |
FY28 |
Walla Walla: |
Little Goose – Transformer Replacement |
FY27 |
Walla Walla: |
Lower Monumental – Transformer Replacement |
FY27 |
Walla Walla: |
Lower Granite – Transformer Replacement |
FY27 |
Wilmington: |
Island Creek – Transformer Supply |
FY24 |
Wilmington: |
Island Creek – Transformer Switchyard Install |
FY26 |
Turbine Oil Accountability and Replacement |
Location |
Description |
Date |
Portland: |
John Day – Powerhouse Oil Detection System |
FY25 |
Portland: |
The Dalles – Oil Accountability Measures |
FY24 |
Coolers, Piping, and Large Valves |
Location |
Description |
Date |
Little Rock: |
Bulls Shoals – Penstock Fill Valves |
FY28 |
Portland: |
John Day – Unwatering System Replacement |
FY26 |
Tulsa: |
Broken Bow – Generator Air Cooler Piping Replacement |
FY25 |
Tulsa: |
Denison – Penstock/Expansion Joint and Drain Valve |
FY27 |
Tulsa: |
Keystone – Unit 2 Penstock Expansion Joint |
FY27 |
Vicksburg: |
Blakely Mountain – Butterfly Valve Rehab |
FY25 |
Walla Walla: |
Dworshak Emergency Gate Cylinder Seals and Piping Upgrade |
FY28 |