Portland District -- Provides engineering services to the Pacific Northwest and Nation to strengthen our security, promote a strong economy & enhance environmental sustainability. The District encompasses nearly 97,000 square miles of land and water in Oregon and southwestern Washington. The District’s future is tied to helping to balance the region’s competing needs for navigation, flood damage reduction, hydropower, fish and wildlife habitat, disaster recovery, irrigation and recreation. This is accomplished by improving and maintaining navigation for economic development and safety, preventing & reducing flood damage, restoring, enhancing & maintaining ecosystems, generating reliable and efficient hydropower, regulating activities in wetlands and waterways, providing Corps-wide expertise in hydroelectric planning and engineering, and by providing safe and healthful recreational opportunities for the public.
Web: https://www.nwp.usace.army.mil/Business-With-Us/
Anticipated
NAICS |
Location |
Project Title and Description/Location |
Fiscal Year |
* Est. Value |
* AC Strategy |
541330
|
NWD
|
Photogrammetric and LiDAR SATOC
|
Q2 24
|
$5M
|
SB
|
541330
|
Portland, OR
|
Pile Dike AE Single Award Task Order Contract
|
TBD
|
$5M
|
SB
|
541330
|
Portland & White City
|
VA Construction Services MATOC (non-Brooks Act)
|
Q3 24
|
$25M
|
SDVO
|
541330
|
Portland & White City
|
VA Construction Services MATOC (Brooks Act)
|
Q3 24
|
$25M
|
SB
|
332312
|
Dexter, OR
|
Intake Gantry Crane
|
Q4 24
|
|
TBD
|
332312
|
Cascade Locks, OR
|
Spillway Crane
|
Q4 24
|
|
TBD
|
237990
|
OR/SW WA
|
Coast/River Clamshell Dredging
|
Q3 24
|
$5M-$10M
|
SB
|
237990
|
Coos Bay, OR
|
Coos Bay Clamshell Dredging
|
Q3 24
|
$5M-$10M
|
SB
|
237990
|
OR/WA/CA
|
West Coast Hopper Dredging
|
Q3 24
|
$50M-$100M
|
F&O
|
336611
|
TBD
|
Essayons Maintenance & Repair Contract
|
Q3 24
|
$10M-$25M
|
F&O
|
336611
|
TBD
|
Yaquina Maintenance & Repair Contract
|
Q3 24
|
$5M-$10M
|
F&O
|
237990
|
SW WA
|
Mt St Helens Sediment Retention Structure
|
Q3 24
|
$10M-$25M
|
F&O
|
237990
|
SW WA
|
Mt St Helens Fish Collection Facility
|
Q1 26
|
$25M-$50M
|
F&O
|
237990
|
OR/SW WA
|
Dredged Material Facilities (DMMP Implementation)
|
Q1 24
|
$1M-$5M
|
SB
|
237990
|
SW WA
|
Columbia River Channel Improvements
|
Q3 24
|
$1M-$5M
|
F&O
|
237990
|
SW WA
|
Baker Bay Pile Dikes
|
Q4 24
|
$10M-$25M
|
F&O
|
237990
|
OR/SW WA
|
Skamokawa Pile Dikes
|
Q1 25
|
$10M-$25M
|
TBD
|
237990
|
OR/SW WA
|
Cottonwood Pile Dikes
|
Q4 24
|
$10M-$25M
|
TBD
|
237990
|
Cascade Locks, OR
|
BON 1 & 2 Control Room Fire Protection
|
Q3 24
|
$1M-$5M
|
WOSB
|
237990
|
Cascade Locks, OR
|
Bonneville Dam Spillway Rock Removal FY24
|
Q3 24
|
$500K-$1M
|
SB
|
237990
|
Cascade Locks, OR
|
BN Power Plant 1 Headgate Repair Pit Rehabilitation
|
Q1 24
|
$1M-$5M
|
SB
|
237990
|
N. Bonneville, WA
|
BN Washington Shore Fish Ladder Modification
|
Q3 24
|
$5M-$10M
|
TBD
|
237990
|
Cascade Locks, OR
|
Bonneville Dam Spillway Gate Repair & Storage Pits (D-B)
|
Q1 24
|
$5M-$10M
|
SB
|
238210
|
Cascade Locks, OR
|
Bradford Island Service Bldg PRQ Switchgear Upgrade
|
Q3 24
|
$1M-$5M
|
SB
|
332312
|
Cascade Locks, OR
|
Bonneville Dam Trashrack Rehab SATOC
|
Q3 24
|
$10M-$25M
|
SB
|
237990
|
Cascade Locks, OR
|
Bradford Island Fish Ladder Exit Dredging FY24
|
Q3 24
|
$500K-$1M
|
F&O
|
237990
|
Cascade Locks, OR
|
Bonneville Metering Enhancements
|
Q3 24
|
$1M-$5M
|
TBD
|
332312
|
The Dalles, OR
|
TD Intake & Tailrace Crane Rail Replacement
|
Q3 24
|
|
SB
|
237990
|
The Dalles, OR
|
The Dalles Oil Accountability
|
Q1 24
|
$1M-$5M
|
F&O
|
237990
|
The Dalles, OR
|
TD Nav Lock Tainter Valve
|
Q4 24
|
$1M-$5M
|
SB
|
238220
|
John Day, OR
|
John Day HVAC UPGRADES
|
Q1 25
|
$10M-$25M
|
F&O
|
561621
|
John Day, OR
|
John Day Powerhouse Security System Upgrades
|
Q3 25
|
|
SB
|
332310
|
John Day, OR
|
John Day Generator Cooling Water System
|
Q3 24
|
|
F&O
|
238210
|
John Day, OR
|
John Day Turbine Rehab Generator Rewind
|
Q3 24
|
>$500M
|
F&O
|
332412
|
John Day, OR
|
JD Trashrack Rehab SATOC
|
Q3 24
|
$10M-$25M
|
SB
|
333923
|
John Day, OR
|
JD Bridge Crane Rails Repair
|
Q3 24
|
$1M-$5M
|
SB
|
237990
|
John Day, OR
|
JD Control Room Fire Protection
|
Q3 24
|
$1M-$5M
|
WOSB
|
237990
|
John Day, OR
|
JD Nav Lock Wire Rope
|
Q3 24
|
$100K-$500K
|
SB
|
237990
|
Lane Co.
|
Hills Creek Main Unit Breaker & Elec Reliability Upgrade
|
Q1 25
|
$5M-$10M
|
F&O
|
562910
|
Marion Co.
|
BCL Total Dissolved Gas Abatement
|
Q1 25
|
|
F&O
|
332313
|
The Dalles, OR
|
TD Trash Rake Crane - Adams
|
Q1 25
|
|
SB
|
This information is provided to serve as a reference for potential contracting and subcontracting opportunities from the U.S. Army Corps of Engineers. The information is subject to change without notice.
Set aside abbreviations |
|
Woman Owned Small Business |
WOSB |
Service Disabled Veteran Owned Small Business |
SDVOSB |
Small Business |
SB |
Full & Open |
F&O |
Request for Proposal |
RFP |
8(a) sole source |
8(a) SS |
8(a) competitive |
8(a) comp |
*projected and subject to change |
|