NAICS/PSC |
Location |
Project Title and Description/Location |
Fiscal Year |
* Value |
* Set-Aside |
541330 |
Project Location |
Construction Management Services (CMS) Sentinel |
FY24 Q4 |
$249M |
UNR |
562910 |
CONUS, Alaska, Hawaii, and U.S. Territories |
ERS w/ MMRP |
FY24 Q4 |
$29M |
SDVOSB |
562910 |
CONUS, Alaska, Hawaii, and U.S. Territories |
ERS (East) SATOC ‐ NWD and Customers |
FY24 Q4 |
$49M |
SB |
562910 |
NWD and Approved Customers |
ERS MATOC ‐ NWD and Customers |
FY24 Q4 |
$249M |
SB |
541330 |
U.S. |
AE Value Engineering MATOC ‐ NWD |
FY25 Q1 |
$20M |
SB |
541330 |
Worldwide |
Airfield Pavement AE |
FY25 Q1 |
$99M |
UNR |
541330 |
NWD |
Military and Civil AE Services |
FY25 Q2 |
$200M |
UNR |
562910 |
CONUS, Alaska, Hawaii, and U.S. Territories |
ERS |
FY25 Q2 |
$25M |
WOSB |
562910 |
CONUS, Alaska, Hawaii, and U.S. Territories |
ERS |
FY25 Q4 |
$10M |
HUBZ |
237120 |
CONUS and outlying areas |
DB/DBB Fuels |
FY25 Q3 |
$699.99M |
SB |
237120 |
CONUS and outlying areas |
DB/DBB Fuels |
FY25 Q4 |
$300M |
UNR |
237990 |
Longmont, CO |
St. Vrain Creek Flood Risk Management |
FY25 Q1 |
$5M ‐ $10M |
SB |
TBD |
Lower Brule, SD |
Lower Brule North Ecosystem Restoration Element #1 |
FY25 Q1 |
$10M ‐ $25M |
SB |
TBD |
Denver, CO |
Southern Platte Valley Ecosystem Restoration |
FY25 Q2 |
$5M ‐ $10M |
SB |
TBD |
Lander, WY |
Popo Agie River Flood Risk Management |
FY25 Q3 |
$5M ‐ $10M |
SB |
TBD |
Mellette County, SD |
Ring Thunder Road Streambank Stabilization |
FY25 Q4 |
$1M - $5M |
SB |
TBD |
Fremont, NE |
Platte River Nonstructural Flood Risk Management |
FY25 Q4 |
$1M - $5M |
SB |
TBD |
Lower Brule, SD |
Lower Brule North Ecosystem Restoration Element #2 |
FY25 Q4 |
$10M ‐ $25M |
SB |
TBD |
Lincoln, NE |
Deadmans Run Flood Risk Management |
FY25 Q4 |
$5M ‐ $10M |
SB |
237990 |
Garrison Dam, ND |
Spillway Approach Dredging |
FY24 Q4 |
$5M ‐ $10M |
UNR |
237310 |
Gavins Point Dam, NE/SD |
Spillway Bridge Structural Repair and Painting |
FY24 Q3/Q4 |
$1M - $5M |
SB |
237310 |
Fort Peck Dam, MT |
Spillway Bridge Pier Repair and Bearing Replacement |
FY24 Q4 |
$5M ‐ $10M |
SB |
237310 |
Ft Randall Dam, SD |
Spillway Bridge Abutment Repair |
FY24 Q4 |
$500k ‐ $1M |
SB |
TBD |
Oahe Dam, SD |
Stabilize Upstream Spillway Channel Bank |
FY24 Q4 |
$1M - $5M |
SB |
TBD |
Ft Randall Dam, SD |
Powerhouse Restroom Rehabilitation |
FY24 Q1 |
$250K - $500K |
SB |
TBD |
Ft Randall Dam, SD |
Powerhouse Elevator Replacement |
FY25 Q2 |
$500K ‐ $1M |
SB |
238210 |
Garrison Dam, ND |
Crest Road Lighting Replacement |
FY24 Q3/Q4 |
$1M - $5M |
SB |
238290 |
Big Bend, SD |
Powerhouse Elevator Rehabilitation |
FY24 Q4 |
$1M - $5M |
SB |
238210 |
Ft Peck, MT |
PH1 Cubicle Room Switchgear Replacement (15kV SWGR) |
FY25 Q1 |
$1M - $5M |
UNR |
237990 |
Ft Randall, SD |
Draft Tube Bulkhead Seal Replacement |
FY25 Q1 |
$500K ‐ $1M |
SB |
335311 |
Ft Peck, MT |
GSU XFMR Supply |
FY25 Q2 |
$10M ‐ $25M |
SB |
237130 |
Oahe, SD |
Riverdale Feeder Relocation |
FY25Q2 |
$1M - $5M |
SB |
TBD |
Garrison, ND |
Powerhouse Heat Pump Replacement |
FY25Q2 |
$1M - $5M |
SB |
TBD |
Oahe, SD |
Intake Gate Cylinder Replacement |
FY25 Q2 |
$1M - $5M |
SB |
TBD |
Gavins Point, NE |
Surge Tank Roof Replacement |
FY25 |
$1M - $5M |
SB |
TBD |
Ft Peck, MT |
Surge Tank Roof Replacement |
FY25 |
$1M - $5M |
SB |
TBD |
Ft Peck, MT |
Unwatering Pump Replacement |
FY25 |
$500K ‐ $1M |
SB |
TBD |
Big Bend, SD |
Draft Tube Bulkhead Replacement |
FY25 |
$1M - $5M |
SB |
236220 |
Cavalier AFS, ND |
Emergency Power Plant ‐ Fuel Storage |
Advertised |
$10M ‐ $25M |
UNR |
TBD |
Minot AFB, ND |
ADAL South Entry Gate |
Advertised |
$5M – $10M |
SB |
236220 |
US Air Force Academy, CO |
Repair Carlton House (Family Housing) |
FY24 Q3 |
$5M ‐ $10M |
8(a) |
TBD |
Offutt AFB, NE |
557th Weather Wing Standby Power |
FY24 Q4 |
$5M ‐ $10M |
SB |
236220 |
Buckley, CO |
ERCIP Redundant Electrical Supply |
FY24 Q3 |
$5M ‐ $10M |
SB |
236220 |
Buckley, CO |
ERCIP Replacement Water Well |
FY24 Q3 |
$5M ‐ $10M |
SB |
TBD |
Peterson SFB, CO |
Temporary Lodging Facility (Non‐Appropriated Funds) |
FY24 Q3 |
$10M ‐ $25M |
UNR |
236220 |
FE Warren AFB, WY |
Geothermal Test Facility ‐ Slim Well |
FY24 Q3 |
$5M ‐ $10M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 ADAL Ops 1/AMU 1 |
FY25 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 Environmental Protection Shelters – 60 Row North |
FY25 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 Alert Apron Expansion ‐ East |
FY25 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 Convert PRIDE Hangar to B‐21 Parts ‐ FSRM |
FY25 |
$10M ‐ $25M |
SB |
236220 |
Ft Carson, CO |
D/B Ambulatory Care Center |
FY25 |
$25M ‐$100M |
TBD |
236220 |
FE Warren AFB, WY |
GBSD Consolidated Maintenance Training Facility |
FY25 |
$100M ‐ $250M |
UNR |
236220 |
Buckley SFB, CO |
Power Independence, Mission Control Station |
FY25 (or FY27) |
$25M ‐ $100M |
UNR |
236220 |
Grand Forks AFB, ND |
Pavements and Maintenance Facility |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 80 Row Environmental Protection Shelters |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 Flight Simulator Phase 2 |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 60 Row Environmental Protection Shelters – South |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 Alert Apron West |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Ellsworth AFB, SD |
B‐21 Alert Facility |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Grand Forks AFB, ND |
Pavements and Maintenance Facility |
FY26 |
$25M ‐ $100M |
UNR |
236220 |
Fort Carson, CO |
SOF Group Headquarters |
FY27 |
$25M ‐ $100M |
UNR |
236220 |
Fort Carson, CO |
Wilderness Road Barracks |
FY27 |
$100M ‐ $250M |
UNR |
236220 |
Schriever SFB, CO |
Security Forces Building Addition |
FY27 |
$5M ‐ $10M |
TBD |
236220 |
FE Warren AFB, WY |
GBSD Operations Group Facility |
FY27+ |
$25M ‐ $100M |
UNR |
236220 |
FE Warren AFB, WY |
Geothermal Power Generation |
FY27+ |
$100M ‐ $250M |
UNR |
562910 |
East Helena, MT |
EPA REGION8 East Helena Residential Lead Cleanup |
FY25 Q1 |
$25M ‐ $50M |
UNR |
562910 |
Pueblo, CO |
EPA REGION8 Colorado Smelter, Residential Lead Cleanup |
FY25 Q1 |
$5M ‐ $15M |
UNR |
236220 |
Prairie de Sac, Wisconsin |
USDA ARS Dairy Forage Research Center 208,000 GSF of New Permanent Construction & 37,000 GSF Renovation |
FY24 /25 |
$25 ‐ $100M |
UNR |
236220 |
University of Nebraska ‐ Lincoln |
USDA‐ARS Nat’l Center for Resilient Precision Agriculture Phase I Headhouse/ Greenhouse |
FY24 /25 |
$10M ‐ $25M |
UNR |
236220 |
University of Nebraska ‐ Lincoln |
USDA‐ARS Nat’l Center for Resilient Precision Agriculture Phase II Research Facility on the UNL campus |
FY26 |
$100M ‐ $250M |
UNR |
236220 |
Madison, WI |
USDA‐ARS Plant Germplasm Research Facility |
FY26 |
$25‐40M |
UNR |
236220 |
ST. Paul, MN |
USDA‐ARS Cereal Disease Research Facility |
FY26‐27 |
$100M ‐ $250M |
UNR |
236220 |
Ft Harrison, MT |
VAMC Central Utility Plant and Parking Structure at Ft Harrison |
FY25 Q2 |
$75 ‐ $100M |
UNR |
236220 |
Ft Harrison, MT |
VAMC Sesmic Renovations at Ft Harrison VAMC |
FY26/28 |
Over $500M |
UNR |
236220 |
Golden, CO |
DOE Rocky Flats Visitor Center Renovation |
FY25/ 26 |
$10M ‐ $25M |
UNR |
236220 |
Grand Junction, CO |
DOE Field Service Center Renovation |
FY25/ 26 |
$10M ‐ $25M |
UNR |